1:Material Control
1.1:Confirm Info :
1.1.1:Check steel mill tag information ,
1.1.2:Check whether the information on the original steel tag is consistent with the incoming information :
Steel mill ,Material Code ,Furnace No. ,Weight ,Diameter
1.2 Size and appearance quality inspection :
1.2.1 Size :
Confirm Diameter tolerance levels comply with the requirements .
Confirm Roundness tolerance levels comply with the requirements .
1.2.2 Appearance :
Check Rusting Level
1.2.2 Physical and chemical propertie :
Cut :Cut Material Head and End ;
Coldupsetting Test :The material can not crack after pressing to 1/2 height ;
Heat erosion :No visible crack after corrosion by hydrochloric acid ;
1.2.3 Microstructure :
To detect the chemical composition of incoming materials with spectrograph, it must meet the standard requirements
1.3 Material Storage :
Incoming material shall be properly stored after incoming inspection confirms that the product is qualified;
The storage location requires a pad to prevent wear and tear;
Different materials are divided into regions;
Avoid wear and tear of forklift rack and material during transportation;
Materials stacked to prevent high extrusion deformation of each other;
Material inspection before receiving.